Adding a downstairs WC is one of the most useful changes to a family house. The cost and the complexity are decided almost entirely by drainage, and that question is worth answering before anything else.
Answer the drainage question first
Everything else about a cloakroom – the suite, the tiling, the basin, the door – is straightforward. Drainage is the variable, and it can change the job substantially.
- Find the soil stackInternal or external, and where it runs. That is the destination for WC waste.
- Measure the horizontal distanceFrom the proposed WC position to the stack.
- Check the available fallA soil branch needs a consistent gradient within defined limits. Too shallow and solids are left behind; too steep and water runs away from them, which is equally bad.
- Check the floor constructionSuspended timber gives you a void to run in, and you have to work with the joists rather than through them. Solid concrete means either a shallow pan arrangement, raising the floor, or cutting – which is a much bigger job.
- Establish the drain invert levelIf the connection point is higher than the WC outlet route allows, gravity is not available.
- Identify the water supply routeCold to the cistern and the basin; hot to the basin if you want it, which is not mandatory.
- Check ventilationA cloakroom with no openable window needs mechanical extract, usually with an overrun.
The classic cloakroom position, and it is classic because it is usually the only spare space. It is also frequently a long way from the stack and on a solid floor, which is exactly the combination that makes a macerator the realistic answer. Worth establishing early rather than after the door has been bought.
Gravity or pumped
| Gravity | Macerator | |
|---|---|---|
| Waste pipe | Large bore, consistent fall | Small bore, flexible routing |
| Position | Constrained by the stack | Almost anywhere with power |
| Power | None needed | Required – no power, no WC |
| Noise | None | Audible while running |
| What goes down it | Anything a WC will take | Waste and paper only |
| Failure | Very rare | A mechanical item that will eventually need attention |
| Cost | Lower if the route exists | Lower if creating the route would be major work |
| Selling the house | No comment from anyone | Some buyers and surveyors are wary |
Gravity is better where it is achievable. Where it would mean cutting a solid floor or running a long shallow branch that will not work properly, a macerator is a legitimate answer and it is what makes some cloakrooms possible at all – see macerators and pumped WCs.
Fitting a usable room into a small space
Cloakrooms are small, and the difference between one that works and one that irritates is a few decisions.
- Door swing. An inward-opening door eats the floor area you need to stand in. Outward, sliding or a pocket door frequently transforms a tight cloakroom. Also consider whether somebody who has been taken ill could be reached if the door opens inward – that is a genuine argument for outward.
- Short projection pan, which gives back valuable floor depth against a standard one.
- Wall-hung or back-to-wall, with a concealed cistern in a frame. Neater, easier to clean, and the frame takes depth from the room – so it suits a room with length rather than width.
- Corner basin or a small semi-recessed basin. Cloakroom basins do not need to be large; they need to be usable without splashing the wall.
- Tap position. A tall monobloc on a small basin sends water everywhere. A short spout suits it better.
- Cold-only basin is permitted and it saves running a hot pipe a long way for a tap that will be run for fifteen seconds. Whether you want it is a comfort question rather than a regulatory one.
- Light and extract on the same switch with a timer overrun, where there is no window.
- Somewhere for a toilet roll and a hand towel that is not an afterthought drilled into new tiling.
Things easy to get wrong
- Cutting joists to run the soil pipe. Notching and drilling are limited for structural reasons, and a soil pipe is large. The pipe route has to work with the joists – which sometimes means the WC moves.
- Inadequate fall, which produces a WC that needs two flushes and blocks regularly. It cannot be corrected afterwards without redoing the branch.
- Excessive fall, which leaves solids behind as the water outruns them. Equally a problem and less intuitive.
- No isolation valves, so the whole house has to be drained to change a tap washer.
- A concealed cistern with no access, which is exactly the same mistake as a macerator with no access panel and produces exactly the same outcome.
- No extract, in a windowless room, which is a Building Regulations requirement and also a matter of simply being habitable.
- Forgetting the basin waste, which also needs a route and a trap, and which is easier to solve than the WC but is not free.
- Tiling before testing. Everything gets filled, pressure tested and left before anything is closed up.
Concealed cistern frames have an access point behind the flush plate for the valve. That is adequate for the valve and it is not adequate for everything. If there are isolation valves or a macerator behind the boxing, put a removable panel in front of them.
Notification and the practical bits
Adding a WC is generally notifiable work under Building Regulations – the drainage connection, the ventilation and any structural alteration are the reasons. That is normally handled by a building notice or a full plans application through the local authority, and it is straightforward. Electrical work in a bathroom or cloakroom also has its own requirements.
Sequence that keeps a cloakroom job short:
- Confirm drainage before anything else, because it determines the layout and the budget.
- Agree the exact positions on site, with the suite present, not from a drawing.
- First fix – waste, supplies, electrics, extract ducting.
- Test and leave under pressure before closing anything up.
- Boarding, tiling, decoration.
- Second fix – suite, basin, taps, extract, accessories.
- Commission and demonstrate – where the isolation valves are, how the extract overrun works.
See also bathroom renovations and bathroom layouts and soil pipes.
Thinking about a downstairs WC? The drainage question decides everything else – worth answering first.
Questions we get asked about this
Can I put a cloakroom under the stairs?
Usually, and it is the most common position. Whether it can drain by gravity depends on the distance to the stack and the floor construction – under-stairs positions frequently end up pumped.
Do I need building regulations approval?
Adding a WC is generally notifiable – the drainage connection, the ventilation and any structural work are why. It is normally handled by a building notice and it is straightforward.
Does a cloakroom basin need hot water?
Not as a requirement, and a cold-only basin is permitted. Whether you want one is a comfort question – running a hot pipe a long way for a fifteen-second wash is worth thinking about.
Do I need an extractor fan?
In a room with no openable window, yes, and normally with a timer overrun. It is a Building Regulations requirement and it is also what makes the room pleasant to use.
Which way should the door open?
Outward, sliding or a pocket door usually transforms a tight cloakroom, and it also means somebody taken ill inside can be reached. An inward door eats the floor area you need.
Is a concealed cistern a good idea?
Neater and easier to clean, and it takes depth from the room. Make sure anything behind the boxing that might need attention has a removable panel in front of it, not just the flush plate aperture.
What happens when you call
Call and describe it
You speak to an engineer, not a call centre. Most jobs can be narrowed down on the phone.
We look at it properly
A real diagnosis before a price, and a straight answer if it is not worth doing.
A written quote
Itemised, so you can see what you are paying for.
The job, and the paperwork
Certificates where the work needs them, and what will need attention next.
Where we do this work
Across Norwich and the whole of Norfolk. If you are on the edge of the county, call and ask — we will tell you honestly whether we are the right people.
- Norwich
- Wymondham
- Dereham
- Attleborough
- Aylsham
- North Walsham
- Cromer
- Diss
- Loddon
- Long Stratton
- Watton
- King's Lynn
Need this doing?
Call and describe the problem — you will speak to an engineer, not a call centre. Written quotes, no estimates over the phone.